NAVIGATION

  1. From the Main Menu, click Administrators/Contract Instructions
    OR

    From the Main Menu, click
    Project Lists.  Click next to project in list, click Project Home button.  Note:  The project's home page will display.

  2. On the dropdown menu, click Procurement/Contract Instructions.
    Note: The project's contracts will list in the display view.

  3. Click next to Contract Number/Name/Role in display view list.
    Note: The contract's VOs and CMs will list in the details view with the 1st line of the description, date last modified & $ value.

 

Add a New Contract Memo

This function enables the creation of a new contract memo.

When there are 10 or more items to select from a list, the 'Filter by' box will display.  'How to use Filter By'

 

  1. Click New at the bottom of the list in the details view.  Note:  A popup window will display requesting the contract instruction type.

  2. Click next to Contract Memo, click Select or Cancel to close the window.  Note: The blank Contract Memo will display in details view.

  3. Enter primary consultant Reference Number in .

  4. Enter the Issued Date (the date the CM was initiated) by either clicking on and selecting date or enter date in .

  5. Select Status from the .

  6. Enter the Authorised Date (the date the CM was authorised) by either clicking on and selecting date or enter date in .
    Note: The system will automatically insert today's date if left blank after clicking
    Save.

  7. Select person who authorised the CM from the Authorised By .

  8. Enter the Summary Description in the .  
    Note: The first line of the description will appear in the contract instructions list.

  9. Select Cause from the .  If 'Other' enter cause in .

  10. Enter Adjustment Amount to the PC Sum in the .  Note:  The adjustment amount will not show in the list.

  11. Click to indicate whether the adjustment Increases or Decreases the PC Sum.

  12. To Add an Attachment, click Browse to locate file (e.g. documents, drawings etc).  A Choose File dialogue window will display, use the Look In to locate the directory and document/file.

  13. Click on the file name, click Open to select file location and name.
    Note: The open attachment image, name of file and a remove box will display under the
    Browse button after you have clicked Save.  Repeat steps 10 & 11 to add another attachment.

  14. Click Save.
    Note:  Contract Memo will save and display in the details view with CM number, accepted contract sum value, current contract sum value, PC sum value, initial PC adjustment total value, PC sum adjustment sum value and attachment file names.  If you did not click Save, all changes will be lost.

  15. Click List to go back to contract instructions list.

 

Navigation Buttons & Screen Items