NAVIGATION
From the Project Home Page dropdown menu, click Time/Program. Note: The Project Program will display.
Project Program
This function enables team members to update the Project Program.
Click Update button at the bottom of the screen. Note: Hover over column headings to display heading descriptions. A red flag icon displays when an update has been made. Hover over flag to display the person and date the update was made.
Select the Project
Phase from the .
Enter the Phase
Dates by either clicking on and selecting date or
enter date in
Note:
The
Actual Start dates for each phase (except documentation) are based on
events within the system that are automatically generated.
Click Save, or click Cancel to discard changes.
If Save
is selected a popup window titled Update
Brief/Plan will display. If
a Baseline
has not been created a will display for selection. Note:
Only select
if creating a Baseline. Once the Baseline has been selected
this option will not display.
Select Reasons
for Change using the .
If applicable enter Comments
to support the reasons in the
Click Save to save program changes. Note: The screen will display the initial program screen.
OR
click Cancel to continue program changes.